Monet Logo
™
2026.10.08

From Brief to Approved Booth Design, Step by Step

Author
Juliano Wahab
CEO, Monet
Wireframe booth design revisions along a timeline, the longest wait for client approval marked in red

This walkthrough follows a made up exhibitor's stand from the first brief to the client's yes. It gives example dates and hours for each stage. It shows how to log each round of changes in the client's words. It shows what to record at approval. You get a log and a timeline to write up a project of your own.

Fourteen days. In this made up example, that is how long a client took to approve one stand. Only 17 hours of that was work. So where did the rest of the time go?

A booth design case study is only useful if it shows where the time went. This walkthrough logs one stand, designed in Monet, from the first brief to the client's yes. The exhibitor, the show and every date and hour below are made up to show the method. Use the same log to write up a real project of your own.

A made up exhibitor and show

The example exhibitor makes sensors for factories. It has booked a corner stand, 6 by 6 meters, with two open sides. The height limit is 4 meters. On the exhibitor's side, a marketing manager and a product lead run the project. On the design side, there is one designer and a project lead.

The brief

Check the brief against the one page brief in How to Brief an Exhibition Stand Designer. Mark every gap. A gap found in the brief costs one question. The same gap found after the first concept costs a whole round of changes.

In the example, the brief leaves out two things. It does not say how many people the meeting area must hold. It does not mention storage for brochures and giveaways. Both turn into rounds of changes later, and the log shows it.

The first concept

In Monet, the first concept is a stand made from a prompt. It is placed to scale on the hall plan. The renders, the plan and the elevations all come from the same model. The clock starts when the brief arrives, not when design begins.

In the example, the brief arrives on day 0. The first concept is shown on day 3, after 7 person hours of work. Person hours add up the time of each person.

Each round of changes

Every round goes in one log. Write each request in the client's words, not yours. Then the log shows what was asked, not what was understood. Hours to respond count each person's time. Count from the request to the new version shown. Copy the log. The rows are invented.

RoundDay askedRequest, in the client's wordsHours to respondWhat changed (plan, renders, drawings)Day shown
1Day 5We need room for six people in the meeting area.3Meeting area made bigger in plan, renders and drawingsDay 6
2Day 8Where do the brochure boxes go?2Storage added behind the back wallDay 9
3Day 11Can the product display face the main aisle?4Display turned and counter movedDay 12

In Monet, one change updates the plan, the renders and the drawings. So each round's views match. Name every file with its round and date. Then nobody works from an old version. In the example, rounds 1 and 2 trace straight back to the two gaps in the brief.

The client's yes

At approval, record four things. Record the date and who approved. Record the exact version approved, and what they looked at.

In the example, the marketing manager approves version R3 on day 14. She saw a walkthrough video and the front elevation. That is a drawing of the front, seen straight on. Want a yes in one meeting? See how to present an event design to a client.

The booth design timeline

StageDayDays since the briefHours
Brief receivedDay 000
First concept shownDay 337
Round 1 shownDay 663
Round 2 shownDay 992
Round 3 shownDay 12124
ApprovalDay 14141

Days are calendar days from the brief. Hours are person hours across both teams. In this invented timeline, 17 hours of work sit inside 14 calendar days. Most of that time is spent waiting for decisions. So that is where to look first.

Compare with other stands only if you have records of projects that are alike. Say how many projects the median covers. Hours are counted the same way as in how to measure planning time saved with AI.

What the log is for

Go back to the fourteen days. The log shows that two rounds came from gaps in the brief. It shows that most days were spent waiting for a decision. Next time, fill the gaps before the first concept. Book the decision dates up front.

After approval, the drawings go to the builder. What your stand builder needs from you covers that handover. Track your next stand with the same log and timeline.

Monet makes booth design from a prompt, placed to scale on the hall plan, with renders and drawings from one model. Its Best Place to Exhibit tool helps exhibitors choose where to exhibit. Get started for free on Monet.

:: Share